NO.1 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side
of your split screen, using the drop down menu, to reference during your response/choice of
responses.
Select the statement that best describes the method to estimate the cost of the new rides:
A. Break down the technology into components
B. Call vendors for quotes
C. Use historical data from past projects
D. Adjust known data from existing rides
Answer: D

AACE International   CCPガイド   CCP   CCP無料更新

NO.2 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
When analyzing a precedence diagram schedule, the "backward pass"
A. Allows total float to be calculated
B. Determines the duration of each activity
C. Calculates the earliest allowable start and finish times for the activities in the schedule
D. Allows activities to finish as soon as all their 'predecessor' relationships are satisfied
Answer: C

AACE International試合   CCP内容   CCP必要性   CCP認定資格   CCPブロンズ教材

NO.3 An agricultural corporation that paid 53% in income tax wanted to build a grain elevator
designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income
generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
How many years will it take to earn $400 in interest on $800 at 4% compounded annually?
A. 10 years
B. 11 years
C. 12 years
D. 13 years
Answer: A

AACE International   CCP技術試験   CCP必要性   CCP参考書勉強

NO.4 Cost performance index (CPI) is defined by AACE International as: (assume no change in
budgeted quantities)
A. ACWP/BCWS
B. BCWS/BCWP
C. ACWP/BCWP
D. BCWP/ACWP
Answer: D

AACE International会場   CCPブロンズ教材   CCP   CCP必要性

NO.5 Meetings require:
A. Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the
total physical and human setting of the meeting
B. Goals, an agenda, preparation, conclusions, control and conversations that are relevant
C. Goals, an agenda, preparation, control, good listening skills and relevant discussions
D. Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where
appropriate
Answer: B

AACE International書籍   CCP   CCPテスト   CCP

NO.6 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side
of your split screen, using the drop down menu, to reference during your response/choice of
responses.
Why is a +/- notation necessary when developing an estimate?
A. Contingency cushion
B. It makes up for the lack of time to develop a real estimate
C. It is a government requirement
D. There are unknowns that affect the final cost of a project
Answer: D

AACE International模試エンジン   試験番号 CCP   CCP   CCPトレーニング費用

NO.7 The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side
of your split screen., using the drop down menu, to reference during your response/choice of
responses.
What is the range of unit costs?
A. $21.57
B. $26.65
C. $48.22
D. $485.00
Answer: D

AACE Internationalサンプル問題集   CCP   CCP勉強法学校   CCP会場

NO.8 A major theme park is expanding the existing facility over a five-year period. The design phase
will be completed one year after the contract is awarded. Major engineering drawings will be
finalized two years after the design contract is awarded and construction will begin three years after
the award of the design contract. New, unique ride technology will be used and an estimate will need
to be developed to identify these costs that have no historical data.
The following is NOT an advantage of the critical path method:
A. The ability to determine cost overruns of critical path activities
B. The ability to identify activities that cannot have their schedules slip if the desired project end date
is to be achieved
C. Reveals activities that additional resources need to be dedicated toward
D. The ability to show slippage in the progress of key activities
Answer: A

AACE International   CCP   CCP関連資料

もしCCP認定試験を受験したいなら、CCP試験参考書が必要でしょう。ターゲットがなくてあちこち参考資料を探すのをやめてください。どんな資料を利用すべきなのかがわからないとしたら、Pass4TestのCCP問題集を利用してみましょう。この問題集は的中率が高くて、あなたの一発成功を保証できますから。ほかの試験参考書より、この問題集はもっと正確に実際問題の範囲を絞ることができます。こうすれば、この問題集を利用して、あなたは勉強の効率を向上させ、十分にCCP試験に準備することができます。

今あなたが無料でPass4Testが提供したAACE InternationalのCCP認定試験の学習ガイドをダウンロードできます。それは受験者にとって重要な情報です。

CCP問題集の品質を確かめ、この問題集はあなたに合うかどうかを確認することができるように、Pass4TestはCCP問題集の一部のダウンロードを無料で提供します。二つのバージョンのどちらでもダウンロードできますから、Pass4Testのサイトで検索してダウンロードすることができます。体験してから購入するかどうかを決めてください。そうすると、CCP問題集の品質を知らないままに問題集を購入してから後悔になることを避けることができます。

CCP試験番号:CCP
試験科目:「Certified Cost Professional (CCP) Exam」
一年間無料で問題集をアップデートするサービスを提供いたします
最近更新時間:2015-05-03
問題と解答:全115問 CCP ファンデーション

>>詳しい紹介はこちら

 

ただ一つの試験の準備をするだけで時間をたくさん無駄にすることをやめてください。はやくPass4TestのCCP問題集を入手しましょう。この問題集を持っていたら、どうやって効率的に試験の準備をすべきなのかをよく知るようになります。このCCP問題集はあなたを楽に試験に合格させる素晴らしいツールですから、この成功できチャンスを見逃せば絶対後悔になりますから、尻込みしないで急いで行動しましょう。

Pass4Testが提供したAACE InternationalのCCPトレーニング資料はあなたが自分の夢を実現することを助けられます。 Pass4TestはすべてのAACE InternationalのCCP試験に受かるための資料に含まれていますから。Pass4Testを手にすると、あなたは安心に試験の準備に身を投げられるようになります。Pass4Testは高品質なトレーニング資料を提供して、あなたが試験に合格することを保証します。明るい未来を準備してあげます。

購入前にお試し,私たちの試験の質問と回答のいずれかの無料サンプルをダウンロード:http://www.pass4test.jp/CCP.html

投稿日: 2015/5/4 7:08:26  |  カテゴリー: AACE International  |  タグ: CCPAACE International